Tower Crane Dismantling Method Statement Now
The tower crane must be dismantled in the exact reverse order of its erection, strictly following the manufacturer’s manual. Step 5.1: Initial Preparation and Counterweight Removal
Sling and dismantle the jib in sections, often using the mobile crane to lower them to the ground.
Attach the rigging to the tower head, unbolt its connection from the slewing ring, and lift it clear.
Fall Protection: Full-body harness with dual lanyard and shock absorber (mandatory for all riggers working at heights).
Disassemble the base chassis or unbolt the anchor mast section from the concrete foundation. Clean and secure all reusable foundation anchor hardware. 7. Safety Measures and Emergency Procedures Fall Prevention tower crane dismantling method statement
Responsible for operating the tower crane safely during its final self-dismantling steps (such as balancing the jib) until control is transferred entirely to the assist crane.
Controls the lifting operations via radio communication or hand signals, ensuring secure rigging of all components.
Ensure all necessary permits and third-party certifications for equipment and personnel are in place. 2. Equipment & Personnel
Disconnect any remaining electrical control cables bridging the cabin and lower mast. The tower crane must be dismantled in the
Before any components are removed, the following must be verified: Tower Crane Dismantling Method Statement | PDF - Scribd
Hydraulic pin pushers and heavy-duty sledgehammers (non-sparking). Impact wrenches and calibrated torque wrenches.
(or local equivalent lifting and crane regulations). BS 7121 Code of Practice for Safe Use of Cranes .
A fully stocked first-aid kit and designated rescue equipment (e.g., gotcha rescue kit) must be present at the base of the crane. 7. Restoration and Site Clean-Up Fall Protection: Full-body harness with dual lanyard and
Before work commences, several logistical and safety hurdles must be addressed:
Remove the retaining pins/bolts securing the counterweight block.
Review the original erection method statement and the crane manufacturer’s instruction manual to understand structural limitations.